Forestream Stairs Construction Status
June 21st, 2012
                
										The Forestream Stairs Construction Activity Status: 
                   
			- Helical piles have been completed and fully installed.
- Due to multiple delays during the shop drawing review stage, metal fabrication was delayed.
- As of now, we are targeting to have the fabrication completed by middle of July.
- Installation of the stairs beginning the week of July 16th.
- Site restoration will be the last element of the project, and will complete the project by the end of July.